Npv calculations of project a & b; with explanations

Calculate the project cash flow generated for Project A   and Project B using the NPV method.       Which   project would you select, and why?   Which   project would you select under the payback method? The discount rate is 10%   for both projects.   Use   Microsoft® Excel® to prepare your answer.   Note   that a similar problem is in the textbook in Section 5.1.   Calculate   the project cash flow generated for Project A and Project B using the NPV   method (Show your calculations): .   Project   A: Invest $10k today and receive $5k at the end of this year and for another   2 years (in 12 mos, in 24 mos, in 36 mos), for total cash inflows of $15k.   Project   B: Invest $55k today and receive $20k at the end of this year and for another   2 years (in 12 mos, in 24 mos, in 36 mos), for total cash inflows of $60k.   Sample   Template for Project A and Project B:    

0 replies